We’ve just completed a significant project that involved installing 136 power poles as well as stringing 56,000 metres of new conductor wire supporting Abergeldie Complex Infrastructure as part of the Transport for NSW AC Feeder Upgrade project between Sefton and Revesby, in Sydney’s west.
Each pole weighed over four tonnes, reaching up to 23 metres in height which required us to use a 40-130T crane to install each pole.
The project is an important and necessary means of enhancing the Sydney Trains network, to ensure our communities have the infrastructure and connectivity they need to live their best lives.