Ausconnex is pleased to have Road and Rail Excavations Pty Ltd supporting us on this high voltage substation connection.
Road and Rail will bring their civil expertise to the project, supporting the installation of the 36km of high voltage cable and 12km of fibre with:
🚧 11.5km of open cut trenching
🚧 9 horizontal directional bores
🚧 Construction of 11 large joint bays
🚧 Installation of 36km of transmission cables